Centro Oeste aqueduct construction.
Digging for foundations: 325,000 m3. Filling soil: 244,900 m3. Concrete: w / Elem. premolded: 854m3. Concrete structures: 8,560 m3. Water treatment plant capacity: 242 1 / sec. Intake works, Hº Aº viaduct 250 m long and forebay
47.687.750
DOWNLOAD SUPERCEMENTO ACTIVITIES
afaoadmin :
Acueduct Centro Oeste
Acueduct Centro Oeste
Where
Snata Fe, Argentina
Work
Centro Oeste aqueduct construction.
Description
Digging for foundations: 325,000 m3.
Filling soil: 244,900 m3.
Concrete: w / Elem. premolded: 854m3.
Concrete structures: 8,560 m3.
Water treatment plant capacity: 242 1 / sec.
Intake works, Hº Aº viaduct 250 m long and forebay
Amount
47.687.750